wendy_89, Hatfield
Answer from tradesperson:
Our quote was made based on the drawings made by the client. It needed to be amended due to the numerous details not in accordance with Building Regs. We booked an inspection with a Building Control before the start due to the nature of the work. The surveyor required additional works and an amended quote was sent. The client did not want to accept the extra costs and encouraged us to start without the amended Building Notice. We stated in an e-mail that we were not going to start until the new Building Notice was submitted. The client has never replied but 4 months later (!) marked on Mybuilder that we won a job and left a negative feedback. Let's not comment this, anybody who reads our reply can judge whether it was fair or not.