Timescale on following job?

Anonymous user 03/03/2024 - 2.58 PM

Anyone who is in the building trade/knows people in the trade can you answer this question for me! How long would it take one plasterer to do the following: 1. Skim a room - 4' x 3' 2. Skim a room - 19' x 12' & Plaster over Artexed ceiling in the same room 3. Skim a room - 21' x 12' & Skim the ceiling 4. Skim a room - 18' x 10' 5. Skim a room - 10' x 17' Also lay 2 DPM & layer of latex covering.

Are you a tradesperson and able to answer this question?

1 Answer

Anonymous user

Hi Laurie Depending on how many plasterers & labourers are doing the job. One man and labourer should take approx 7-8 days based on what you have stated. This could be extended, depending on the condition of the walls & preparation required. Kind regards O'Briens plastering
Answered6 February 2013