How much should I expect to pay someone for installing new bathtub, sink with vanity unit and toilet? Also, how long does it take to do the job? I'd like mine done before the end of the year. Many thanks
Are you a tradesperson and able to answer this question?
5 Answers
Chic childrens furniture ltd
Rating: 5 out of 5
Hi
If it’s just a straight swap and just fitting it
Should cost £1200/£1500
Hope this helps
Answered23 November 2026
0
BARIS LONDON LIMITED
Rating: 5 out of 5
For a straightforward like-for-like replacement of a bath, vanity basin, and toilet (using the existing pipework positions), you should typically expect to pay around £600 to £1,100 in labour (excluding the cost of the new suite and any tiling or flooring).
Estimated Timescale:
• Like-for-like swap: Usually takes 1.5 to 2 days to remove the old suite, fit and plumb the new units, and seal everything properly.
• Additional work: If pipework needs moving, walls need making good, or tiling/flooring is included, allow 3 to 5 days.
Answered23 November 2026
0
Hanilles Projects Ltd
Rating: 5 out of 5
Around £800–£1,200 for labour, assuming the existing plumbing and waste connections can be reused and everything is staying in the same positions.
As for project duration, 2-4 days taking into account the above-mentioned.
Answered23 November 2026
0
Essex_Plumbing_and_installatio
Rating: 5 out of 5
Hello, good afternoon.
Regarding the work you listed, including removing the bath, toilet and washbasin, and installing the new ones, I estimate the labour cost would be around £600–£700.
I think the job would take approximately two days to complete.
Thank you.
Answered23 November 2026