French drain coupling into a brick inspection chamber
Graeme Bell 09/11/2026 - 1.48 PM
Hi there. Seeking guidance for the above. What is the appropriate process and materials to connect a perforated French drain pipe into a brick chamber please? Should there be a one way flap value inserted from the pipe at the point of entry along with a u bend to prevent both rats and the smell of the sewers coming to the surface? The French drain is only 4mts long. Many thanks. Graeme
Are you a tradesperson and able to answer this question?
1 Answer
Willow 2000 Ltd
Rating: 5 out of 5
Hi
The connection will depend on the type of pipe coming out of the chamber, these come in different sizes depending on pipe diameter and material used when the chamber was built
As for a none return valve or flap these will not prevent smells I would recommend installing a bottle gully . The U bend will form a seal that in turn will prevent smells. Hope this helps
Good luck
Paul
Answered9 November 2026