What is the minimum time to allow for lime mortar to dry etc

Are you a tradesperson and able to answer this question?

1 Answer

Elliotts roofing NE limited

No reviews yet

Newton Aycliffe
12–24 hours - Initial setting may begin 24–48 hours - Mortar gradually firms up 72 hours - Minimum initial weather protection period 7 days - More substantial strength development 28 days - Significant curing, but not full strength 3 months+ - Strength continues developing
Answered9 October 2026