Hardcore advice (no pun intended)
Stuart Dempster 02/09/2026 - 3.22 PM
Hi, so I'm laying a two track driveway in my garden, two 500mm tracks each 4m long. I've dug down 20cm. Compacted soil by stomping many many times. Laid woven heavy duty porous membrane. 10-15cm of mot type 1. I'm then doing approx 2cm sharp sand followed by interlocking plastic grids, filled with 8-15mm pebbles. My question is, I dont have a compactor for the type one short of size 9 steal cap boots stomping and some 30kg rubble sacks thumped down. It wont be used every night, just if I have no space nearby. Will it be ok or will grids sink? Really dont want to hire compactor (neighbour noise issues already). Cheers