Door canopy
Jason Cowen 20/10/2026 - 8.08 AM
Hi, I'm tiling a small apex door canopy using Tapco slates. Roof width is 640mm including a dry verge system. Tapco tiles =295mm +5mm gap. Can someone tell me the best way to set out the slates horizontally on the eaves + starter course so I don't end up with small slivers of slate at the ends on alternate courses? while try to keep a broken bond pattern. Many thanks.
Are you a tradesperson and able to answer this question?
3 Answers
R N SLATE & LEADWORK SPECIALIST
No reviews yet
Hi pal .. 5mm gap is abit big you want 1-3mm gap .. start in the center and work your way to either gable making sure you have sufficient headlap on your eaves and topper course.. working out from the center will allow you to have a get your cuts for each side out of one tapco on your half cuts. If you get stuck drop me a message , best of luck
Answered20 October 2026
2
Nelson Roofing
No reviews yet
Leave the battens long and lay the slates along dry
Ensure the roof is the same width top and bottom
You will have scope with the tile/ slate and a half
You could also gain more adjustment by using undercloak instead and sealing with mixed sand and cement but I would add wire mesh in the verge first and wet the batten ends
Answered21 October 2026
1
Local roofer services
Rating: 4.9 out of 5
For a 640 mm-wide apex canopy, I’d set the Tapco slates out from the centre line rather than starting with a full slate at one side. This should give you a more balanced finish at both verges 1. Mark the centre line of the canopy at 320 mm Dry-lay the first course to see how the slates finish at each verge Set the starter course so the slate joints on the next course fall approximately halfway across the slates below.
Avoid automatically starting every alternate course with a full slate; adjust the starting position to keep the verge cuts reasonably equal Check the dry verge manufacturer’s requirements and Tapco’s fixing instructions before cutting or fixing the slates
Answered21 October 2026