Question category:
Conservatories
Anonymous user 8 May 2011 - 10.31 PM
As a rule a conservatory base team will dig and lay foundations first,then lay trench blocks below the ground and brick courses above,the last thing they will do is float an oversite (concrete floor) this will take a couple of days to harden so you can stand on it but I usually advise 3 to 4 days before walking on it,usually a finish screed is floated on top of the oversite to give a level floor surface,once the conservatory is fitted you will have to wait a few weeks before you can lay a floor,either check with a damp meter or lay a thick magazine on the floor once its looking dry overnight,if when removed there is a damp patch underneath then its not dry. regards sean
Answered
13 May 2011
Like
If it is just a base for a consevatory, he will get the base laid in a day, as for working of it, you should allow a couple of days to set, although it wont be fully cured. So long as no heavy stuff is chucked about on it, it should be ok, this is normally the practice, as the builder isnt going to wait for it to fully cure, when he can carry on with the build. I would imagine there will be a floor screed laid over afterwards.
Answered
9 May 2011
Like
It is quite possible that the base can be completed in the time frame given by your builder. Once the concrete has been layed he has completed the task at hand apart from any shuttering that has to be removed or not. Depending on what you are going to do with the base is the time you have to leave it before continuing with your project. Normally three or four days is sufficient to leave it before further activity on it. Note if the weather is extremly hot after the base has been completed then a small application of water sprayed on it would not go amiss this helps to stop surface cracking. Under normal circumstances the concrete would take any where up to 56 days to cure according to what specification were applied to the concrete. Hope this helps Regards Ken
Answered
9 May 2011
Like
first cure normally 24 hours after pouring concrete. second cure 10 days final cure 28 days also reinforcing gives concrete more strength.
Answered
26 June 2011
Like