Small bed room, painting including ceiling and door, skirting boards. Could you please provide an estimated time to complete ?
Are you a tradesperson and able to answer this question?
29 Answers
Dave plastering
Rating: 5 out of 5
Hi i do it for 250 plus paint .it sounds a straightforward job fill free to ask me any questions
Answered22 August 2025
3
Handy Helper
Rating: 4.6 out of 5
In my opinion, you would be better off taking two days for this job, but it shouldn't take two full days. Day one put two coats of paint on the walls and ceiling, a mist coat and a top coat. Day two prepare surfaces for gloss coat, job should be finished.
Answered18 August 2025
0
Anonymous user
Two days of work. The first day filling holes and preparing the surface and painting everything twice. The second day making corrections, cleaning up after yourself, and thanking you for work. The price for the job £550
Answered19 August 2025
0
Renovate my space
No reviews yet
All painting job I carry out I ensure prep work is done painting which includes cracks repairs, gaps, level out where required
Apply paint depends on wall condition to ensure an excellent finish as might require upto 3-4 coats to ensure a proper coverage
Answered19 August 2025
0
Frame & Form
Rating: 5 out of 5
For painting a small bedroom, including:
• Ceiling
• Walls
• Door
• Skirting boards
We estimate the job will take 1 full working day to complete to a high standard.
Total Cost: £190 (all labour and materials included).
Answered18 August 2025
0
Anonymous user
Usually about 2 days given time for drying and second coat. Depending on how much prep work needs doing (filling, sanding etc)
Answered18 August 2025
0
Reliable Building Solutions
Rating: 5 out of 5
Only one room, it could easily be done in a day. Thanks
Answered18 August 2025
0
G.D Luxury Painting And Decorating
Rating: 4.7 out of 5
The estimate quote is £350.00, and that includes all Trade materials.
The final cost can vary a bit depending on what prep work is needed—like wallpaper removal, plastering, sanding, filling, doors painting, skirting painting, woodwork painting, how many colours you’d like, and the general condition of the walls.
To give you an accurate quote, I can pop over for a quick assessment, let me know your availability and I will be there.
We also offer a full range of services, including:
• Interior & exterior painting
• Commercial and Domestic
• Plaster / Skimming
• Spray painting
• Full Media wall construction.
• Tiling
• Laminate flooring
• Decorative finishes mese in Italy, textured painting, Venetian plaster, marble effect, alternative for tiles kitchen splash back and bathroom ( shower area included).
We’re fully insured (up to £1 million), and all our work is guaranteed.
To make sure everything lasts and looks great, and for the guarantee we only use top-quality trade paints that we supply.
All the best,
George Dragan
Answered18 August 2025
0
Unidoorsuk Ltd
Rating: 5 out of 5
The estimated time to paint a small bedroom, including the ceiling, door, and skirting boards, is typically 2-3 days.
However, this is a general estimate and the actual time can vary significantly based on several key factors:
1. Preparation is the most time-consuming part:
This includes clearing the room, covering furniture and floors, patching holes, sanding surfaces, cleaning, and applying painter's tape.
The condition of your walls, ceiling, door, and skirting boards plays a huge role. If there's old peeling paint, cracks, or other imperfections, the prep work can easily take a full day or more.
2. Drying Time Between Coats:
Most surfaces (walls, ceiling, woodwork) require at least two coats of paint for a professional-looking, durable finish.
You must factor in the drying time specified on the paint can between each coat, which can range from 1-2 hours for water-based paints to 12 hours or more for some oil-based gloss paints.
3. The Order of Operations:
Painters generally follow a top-to-bottom approach to avoid drips on freshly painted surfaces. The typical order is:
Ceiling
Walls
Skirting boards and door frames
Door
4. Your Experience and Speed:
A professional painter can work much faster than a DIYer.
Using a roller with an extension pole for the ceiling and walls can significantly speed up the process compared to just using a brush.
A breakdown of the time needed for each part:
Ceiling: Painting a standard-sized ceiling can take a few hours, plus drying time between coats.
Walls: Painting the walls can take a few hours per coat, but again, depends on the size of the room and the number of coats.
Skirting Boards and Door: Painting the woodwork often takes a lot of time due to the need for precise brushwork and the multiple coats (primer + topcoats). A single door can take 2-5 hours to paint, including drying time.
In summary, while the active painting time might only be a day, the need for preparation and the drying time between coats almost always extends the project over several days.
Answered18 August 2025
0
Anonymous user
This could take a few hours if you need to repair the wall (I.e filling any cracks/holes). You would need to let the filler/plaster dry before applying an undercoat/white wash. If you do not need to prep the wall, this could take 2-3 hours maximum (allowing time for the first coat to dry). I hope this helps you with your question.
Answered18 August 2025
0
John
No reviews yet
Hi,that work can be done in one day depends if cellings and walls are in good condition and ready for paint but for better quality I prefer to spend 2 days to have only one coat of paint on walls each day.
Answered18 August 2025
0
Bromley Painters
Rating: 5 out of 5
To paint a bedroom either it and small size I will need two days ... On the first day protection will be applied and possibly repairs will be applied to cracks, cracks that you usually find at each job ... the next day the paint will be applied ....
Answered18 August 2025
0
David D.T.M Builders
Rating: 5 out of 5
I would charge £300/£350 it’s 1 full day for a pro - (1–2 days for DIY)
Answered18 August 2025
0
PDRS Decorating
Rating: 4.9 out of 5
More information about room just because is there any cracks in the walls or ceilings & is there any woodwork need filling & undercoated i change £180 aday includes: Labour, Caulk, Wallfiller, Woodfiller.
Answered18 August 2025
0
Anonymous user
I'd say Two Day's Top's, and that's Caulking all Internal Edge's and any Filling, Painting Ceiling and Priming and First Coating Woodwork on Day One then Both Coat's on Wall's and the Final Gloss/Satinwood on Day Two to Finish Up.
Answered18 August 2025
0
Anonymous user
For nice results allow day and half, three coats for long lasting results, price will vary depending on condition of surfaces, amount of prep etc, if there's no issues you will probably be looking at range between 350-450 pounds plus materials.
Answered18 August 2025
0
Dashiell Oliver
Rating: 4.5 out of 5
Painting a room depends on size, standard, location, color, preparations needed etc. (More time More fees)
For a standard small room with low ceilings around 7 to 10 square metres and minor preparations:
(light sand of ceiling, walls, skirting and one door)
And minor filling (one coat on small wholes and imperfections)
2 coats of paint
(All white or multiple colors)
^^
Professional painter will complete in 1-2 days, depending on time of year. Room temperatures and air flow affect the speed of dying time.
More preparations More time.
Having the room clear will always Speed up the process (more protection, More time)
All Materials ready before starting (planning with painter before start date)
Perfection takes time (no matter how damaged or old the areas are) enough time can make it look brand new
"Small bed room, painting including ceiling and door, skirting boards. Could you please provide an estimated time to complete ?"
^^^With out walls
A professional should not take more than a day
Answered18 August 2025
0
Ryan Ostell Painting & Decorating
Rating: 5 out of 5
If the walls are not to do, the ceiling & all woodwork would take 1 day to finish definitely no more, im assuming the door casing is included which isn't mentioned but using water based paint for efficient drying times definitely a one day job
Answered18 August 2025
0
MJR Decorators and maintenance services
Rating: 5 out of 5
Without seeing the room, I would say day one day. Could be extra factor’s depending on the amount of prep, bare plaster, deep colours which could require extra time.
Answered18 August 2025
0
Mike Osborne
Rating: 4.9 out of 5
Hi to paint just the ceiling, door and skirting boards should take around 4/5 hours, add another couple of hours on if needs another coat ! Also need to bear in mind how much prep work is required (rubbing down , undercoating, masking etc) ! Also need to know if the room is empty or not!!
Answered18 August 2025
0
Private maintenance
Rating: 5 out of 5
I will do £250 water based paint without materials for one day job. If the surface underneath is not damaged and only a repainting is needed, it will take me half a day, or three hours.
Answered18 August 2025
0
DK Construction
Rating: 5 out of 5
Good afternoon how are you today ? for full service decorations whole room chargearound £350 : walls , ceiling, skirting boards, window frame if wooden, windowsill if wooden, filing gaps cracks. Wood work: filing,sanding, cleaning of dust and grease .
Answered18 August 2025
0
JPH Decorator
Rating: 4.9 out of 5
If the walls are okay it could take a day it would be £160
Answered18 August 2025
0
Ahmad
Rating: 5 out of 5
Good evening, we can do that, no problem, within a period not exceeding one day, at a cost of 200, excluding painting materials, and the work included at a cost of 250, for your sake, and we will be happy to serve you. Thank you.
Answered18 August 2025
0
Pat Ryk
Rating: 4.9 out of 5
Two days if there’s no filling required. Labour only: £250.
Answered18 August 2025
0
Anonymous user
Ceilings, walls, doors, door frames and baseboards can be painted within 1 day.
Answered15 August 2025
0