Should a builder let you know the price of extras along the way?
Anonymous user 23/02/2024 - 3.52 PM
..
Are you a tradesperson and able to answer this question?
4 Answers
Anonymous user
As a painter and decorator, I can provide you with some guidance on this matter. In general, it is considered good practice for a builder to inform you about any potential additional costs or extras before proceeding with the work. Transparency and clear communication between the builder and the client are essential to avoid misunderstandings and disputes.
When it comes to extras or changes in the scope of work, it's important for the builder to discuss them with you, provide a detailed breakdown of the additional costs involved, and obtain your approval before proceeding. This allows you to make an informed decision and be aware of any financial implications.
In your specific case, if the builder did not clearly communicate to you that the adjustment to the opening for the doors would incur an extra cost, it can be seen as a lack of transparency on their part. If you were not made aware that this modification would result in additional charges, it is reasonable for you to feel surprised and question the fairness of the charges.
To address the situation, I recommend having an open and honest conversation with the builder about your concerns. Explain that you were not informed about the extra cost and that you expected it to be included in the original agreement. Request a breakdown of the additional charges and discuss the matter with them in a calm and professional manner.
It's important to remember that each situation is unique, and there may be specific terms and conditions outlined in your contract that could affect the builder's obligations. If you have a written agreement or contract in place, review it carefully to see if it addresses any provisions for extras or modifications to the original scope of work.
If a satisfactory resolution cannot be reached through direct communication, you may need to seek further advice from a legal professional or consider mediation to help facilitate a fair outcome.
Ultimately, it is advisable to maintain clear communication with your builder throughout the project to minimise the chances of misunderstandings and ensure that any additional costs or changes to the original plan are properly discussed and agreed upon in advance
Answered18 May 2023
1
Leo maintenance
No reviews yet
Whatever happened with the first builder you have to sort this out before you get someone else as you’re finished with the first builder turn off. Do you get the other builder and then you get the bill right you won’t be charged twice and the bill go to high. Thank you
Answered18 May 2023
0
ADR Property Maintenance
Rating: 5 out of 5
If he has had to change the size of the opening then yes it's chargeable, he is doing more work which someone has to pay for. While he. Should have informed you the cost,if he had he stopped the job without doing your new door you would might not be happy there. This is really something that should have been fixed out prior to the job starting. In reality both parties need to communicate fully, for example, informing the builder that you were going with a different door company and the changing the sizes.
Good luck Alex
Answered18 May 2023
0
Anonymous user
If you get the chance at the start you should. And if there any serious expenses along the way you should immediately let the client know and come to and agreement.
Answered19 May 2023