Large concrete slab for workshop shed, should a DPM be used between the MOT type 1 and concrete? If so, what type of sand should be used to go on top of the MOT before laying down the DPM on top? As without sand i think the MOT will perforate the plastic as its very sharp in places plus the weight of the concrete going on top. Cheers

Are you a tradesperson and able to answer this question?

3 Answers

Rdm plastering

Rating: 5 out of 5
Rainham
The sand you should use is sharp Sand leveled out so DPM can be laid safely on top
Answered26 August 2022
12

Anonymous user

From my point of view I would personally lay MOT and compact and after this I would then suggest using ordinary building sand as this is because it compacts Better than sharp sand and the DPM will sit Better on top
Answered2 September 2022
0

Pb plastering

Rating: 5 out of 5
Prescot
use crush and run and whack the crush and run make sure it's at least 4 inches. apply Dpm and install insulation and then apply more Dpm and then concrete to damp
Answered13 September 2022