Foundation step shuttering
Anonymous user 28/02/2024 - 4.05 PM
Hi, The extension foundations needed a step in the concrete , the ground contractor shuttered to the bottom of the trench, the concrete has been poured. Now there is 480 mm deep on concrete then a 30 mm wide gap of contain no concrete (where shuttering is) and then the concrete starts again with a 230 mm step up, hence 710 mm of concrete depth. Is it normal to shutter to the bottom of the trench as I thought that the concrete should be continuous? If not should it be fixed by: jack hammer the 480 mm side down by say 150 mm, then rebar into the step and then concrete over at the step height? Thanks J