Bonding new cement to old brickwork
Anonymous user 28/02/2024 - 4.05 PM
The problem is that the patch of brickwork has had at some point had some dampness which has crumbled two bricks but not all the way through so with the aid of some coloured pigment mixed in with cement I was looking to fill the gap. My question is, what UK product is available to bond the new cement to the brickwork, such as an acrylic fortifier, but which product and who sells them it please?
Are you a tradesperson and able to answer this question?
4 Answers
Thomas oconnor
Rating: 4.8 out of 5
As this has already caused damp you would be better off removing the damaged bricks and re placing them , and depending on where the damp was a bit of re pointing
Answered20 August 2022
7
Classic Brickwork
Rating: 5 out of 5
I agree with Thomas O’Connor answer that removal of the damaged bricks is the best solution. But I wanted to add that before you place the new bricks in, have a good look inside the cavity, you might see what is causing the damp, possibly bridging of the cavity walls.
Answered21 August 2022
1
Norman Styles
Rating: 5 out of 5
I agree, the bricks need cutting out and replacing then repointing
Answered30 August 2022
0
Greg Snape Building
Rating: 5 out of 5
The other answer that has been submitted is the best option. The only thing I would add is that any mortar you use should not be too strong. The weaker the bricks, the weaker the mortar should be.
Answered31 August 2022
0