In what order should I get my jobs done before or after rewiring?

Anonymous user 23/02/2024 - 3.47 PM

Hello I'm looking to get a full house rewire in the future but I also have other plans which may cause just as much disturbances and I don't know in what order to get them done before having all walls plastered and decorated. I'm looking to have done: New floorboards/stairs, Move/Add a radiator and have the central heating pipes redone to clean them up, Interior Insulation work if any, House rewire What order would be most efficient before finishing up and decorating? Thanks

Are you a tradesperson and able to answer this question?

5 Answers

Anonymous user

New wires first 👍
Answered13 May 2022
2

Citelec

Rating: 5 out of 5
Crawley
Agreed with MB Electrical Cabling First ( First Fix)
Answered13 May 2022
0

Anonymous user

Electrical and plumbing/ heating at same time. Woodbutchers next then plaster/ decorate
Answered14 May 2022
0

Gold Electrical and Security

Rating: 5 out of 5
Blackwood
First fix electrical and lay floor boards before plastering. Then after plastering electrical second fix and testing.
Answered15 May 2022
0

Anonymous user

Agreed with above 100% rewire first. If you plan on doing the other works as well then now would also be a good time to plan the layout of your house and have sockets in exactly the right positions. Hope this helps
Answered18 May 2022
0