I have a blockwork with render cavity wall which has 450mm high brick plinth, I'm not quite sure where to place the dpc, should I be placing the dpc in the brick plinth at 150mm above ground level? Or should place it in the blockwork cavity wall itself? Because the plinth is 450mm high should I place the dpc at 450mm above ground level?

Are you a tradesperson and able to answer this question?

3 Answers

Joe Bath

Rating: 5 out of 5
Bath
Where is the level of the internal floor and is it wooden joists or concrete? This will determine where the dpc goes.
Answered23 March 2022
10

Brick & Stonework Services

Rating: 5 out of 5
Weston Super Mare
Horizontal DPC's on outer skin to be at 150mm min above finished ground, eg path level