Anonymous user 03/03/2024 - 3.39 PM

Hello, Looking for some advice. 😆 The house had originally red thick tiles on the window sills, and they hadn't been well looked after (some just not cleaned and protected, some tiled over with a thinner tile and others painted) So before the old windows where renewed I took them out with the hope of replacing them with a pine window board. So my questions are - the thickness is slightly different between the thickness of the tile and the window board, so the window board needs to be raised up slightly so it sits neat and flush with the bottom of the window. What would be a good way of doing this? - which comes first plastering of the rooms and then fitting the sills or fit the sills and then plaster? - and what is a 'normal' overhang of the window sill from the wall? Any advice is much appreciated Rob

Are you a tradesperson and able to answer this question?

4 Answers

Carpenter Jioner

No reviews yet

Coleford
Fit the window board first then plaster
Answered20 August 2021
3

David Evans

Rating: 5 out of 5
Llangammarch Wells
I would use plastic packers 1mm- 6mm available at most building places and pack up to your desired height at the back and do the same at the front until level. I would then put some weight on it and then foam the gap using expandable foam, this will help glue the board down and seal the gap ready for plaster. With pine I would fix it down as well after the foam has set
Answered21 August 2021
0

mint joinery

Rating: 4.8 out of 5
Chorley
my answer window board first then plaster, overang 11/2 to 2 inches, how to fix window bottom ,get a qualified joiner to do it,expirence is evrything ?
Answered26 August 2021
0

Anonymous user

yes window board first. pack window board up just above base of window , with timber packers and level. fix through packers. use expanding foam to fill gap after fixing down.
Answered31 August 2021
0