Ready to hire?
Post your job in minutes, browse real reviews and choose who to speak to.Post a jobNeed some tips or advice?
Ask a questionExtensions
9 months and nothing is really finished
Anonymous user 01/03/2024 - 2.55 PM
Hi after 30 minutes typing I realised that this is limited to 3000 characters. Short version. We employed a contractor to carry out an extension 8x4 metres, plus extensive renovation works, garage roof, conversion 2 ensuites plus main bathroom, new kitchen flooring and so on. Many verbal discussions contract really poor but signed and states any extras to be agreed prior to being undertaken. 9 months later I have over 60 snagging issues, really poor craftsmanship and a builder who only turns up when they fancy. Yes the project was changed after week 3 but builders carried on with architect drawing all extras were discussed but now builder claims they are 15k out of pocket and I'm in a property that is not finished. Can the contractor legally charge me for these extras and is it acceptable to leave the works unfinished. I wish I coukd turn back time but this is where we at 9 months over 50k down the drain and a home that still looks and is a building site. Everything invoiced as an extra we paid for. The extras in question are supposedly because the plan changed about week 3, they have not invoiced us for this, and only mention it whenever I've threatened with legal action. I'm not seeking to claim any monies or any action against the contractor. I just want my job finished and to a good standard.
Are you a tradesperson and able to answer this question?
3 Answers
FMC Builders
PBC Interior Design and Build