tiling onto sand & Cement screed floor (drying time)

Anonymous user 16/03/2024 - 2.40 PM

Hi i have had an extension built with concrete base, 100mm Insulation, UFH and 60-75mm sand & cement (dry mix) screed. It has been drying out for about 2 weeks, 1st 7 days kept the windows shut to try to slow the curing process since then have introduced some heat into the room and opened the windows regularly. we have some minor cracking (to be expected i believe). I am planning to have the floor tiled with 90*60cm tiles. i can't get a clear answer as to drying time, i read the easi-mix (screed supplier) concrete advice and it seemed to indicate 3-4 weeks drying for tiles and approx 90-100 days for wood/laminate. I am assuming that tiles of the grout are slightly porous so the water must continue to escape with tile and hence you can tile significantly earlier that other final floorings? It also seems liquid screed needs more time to dry than the dry mix (sand & cement) ? Am just trying to work out timings as i can fit the kitchen units before tiling but my preference is to tile 1st (i feel it will be a better finish), however 100 days is a long time without a kitchen. Seems a lot of info on the web about drying screed but not always specific regarding the different types of screed. Any advice or thoughts welcome & appreciated Andy

Are you a tradesperson and able to answer this question?

4 Answers

GC Building Services

Rating: 5 out of 5
Canterbury
Hi ... The problem for you is you think it’s ok as it looks dry. You need to be patient!! I wouldn’t recommend laying any floor on top of screed for a minimum of 4 weeks for tiles and the very minimum of 6 weeks for wood or laminate and then you will also need a vapour barrier consisting in a form of painted for solid flooring and foil backed for laminate. If you are thinking of installing underfloor heating underneath the tiles for example then wait at least 6 weeks. You can’t speed up the drying process without causing structural damage which will cost you more in the long run . I’m sorry it’s not the answer your looking for but some process take time , I hope this helps
Answered2 February 2021
15

Classical ceramics ltd

No reviews yet

Bordon
The recommended drying time is 1mm per day to allow the screed to dry correctly If it’s a heated screed then leave for 10days then commission the floor by increasing the heat slowly over 2-3 weeks allow to cool then you can install Hope this helps
Answered12 February 2021
1

Anonymous user

Hi this is not a problem if you are laying tiles or stone, you should be laying schluter ditra 25 directly onto the new screed if done so you can lay ditra membrane onto new screed as long as it can support weight then tiled straight after. The ditra membrane actually slows down the drying process of the screed.
Answered18 February 2021
0

The Wright finish

No reviews yet

Belper
Yes u do need to let it dry for at least 4 weeks but if its cracking put a detra mat down first then tile that will solve your problems even if u have underfloor heating
Answered28 February 2021