Hi Should I put new bathroom doors and frames on before or after I have the bathrooms redone or does it not matter which goes in first. Thanks in advance
Are you a tradesperson and able to answer this question?
4 Answers
G.D.Joiners LTD
Rating: 5 out of 5
Hi personally I would fit the new door and frame before the bathroom got re done and that allows you to either tile or wet wall or whatever finish your doing to the bathroom you can finish it to the new door architrave
Answered19 November 2020
1
Mv carpentry
No reviews yet
It shouldn’t really matter but if your changing the frame I would do it before to minimise any damage to your new bathroom.
Answered19 November 2020
0
Anonymous user
I personally do door frame only before you get bathroom don this way you can finish your tiles and architraves as you want after you finish tiling install the door
Answered19 November 2020
0
Pursercarpentry
Rating: 5 out of 5
The frame first so the wall boards and tiles have something to finish on then the door at the end of the job , all trades should be consulted throughout the ensure the frame is correct width for stud plaster board tiles ect .