Skip to main content

Ready to hire?

Post your job in minutes, browse real reviews and choose who to speak to.Post a job

Need some tips or advice?

Ask a question
Conversions

Changes to the price of a renovation project that were not agreed to beforehand

Anonymous user 16/03/2024 - 2.36 PM

Hi all, I am nearly finished renovating my house and the time has come to settle up with the builder. We originally agreed a quote of around £50k and this has gone up to around £60k. The contract is apparently a standard JCT contract which states: 1. The price does not include the contractor’s costs of dealing with any unexpected problems. As such problems arrive, they will be discussed and the contractor will carry out a careful inspection will provide an estimate to deal with the problem, which will be noted in the specification. 2. If the customer changes the work details the price will be increased or reduced depending on the changes, the contractor will provide an estimate for any changes to work details. 3. The price for the work shown in the work details, together with all the increases or decreases made to it, will be the total price. 4. The elements of the price that are estimated require more information or investigation and will be confirmed with the client before going ahead. In most cases the prices changes have occurred because I have asked for extra work to be carried out. However, we didn't agree to the price of this work beforehand and it generally seems to be quite high. The price of some existing tasks has also been increased. The price for some of these existing tasks were originally listed as an estimates so some change was expected. Others were agreed to as fixed so shouldn't change in my opinion. In both cases we didn't agree on the price change before the work was carried out. Given that we haven't agreed on any price changes beforehand, how do you think we should decide and agree on a fair price in retrospect? I am thinking of maybe getting another builder to review the prices, not sure if this will be much help though. If this does end up in some kind of adjudication proceeding, how much does this typically cost? Thanks very much!

Are you a tradesperson and able to answer this question?

3 Answers

Anonymous user

If you agree to the work and don't agree a price you have entered into an implied contract that leaves you very much at the mercy of the builder. The terms you have quoted do not require any agreement just that you are kept informed. It is very difficult to be sure without seeing the terms in the context of the full contract.
Answered29 October 2020
10

Bespoke Home Design Plastering Specialists

Rating: 5 out of 5
Whitstable
Given the wording of the contract extract, and your admission that the majority of the cost has come from extras which you have requested, the builder is within his right to complete the works as requested. Without requesting quotations for additional works, your existing contract requires you to fulfill the financial obligations agreed too including extras which you yourself have requested.
Answered1 November 2020
0

As above

No reviews yet

Poole
The problem is, yes correctly it's an implied agreement, but both parties have made the mistake of not putting everything in writing
Answered4 November 2020
0