Hi, I recently had my ceiling re skimmed after the first plasterer did a bad job. I went with the new plasterer on recommendation and he assured me he could correct the ceiling. He also did a fresh skim on the walls for me. The result on the ceiling is even worse than before, now Its painted it shows so many lumps and bumps, trowel marks and dips. The walls also aren’t that great but I’ve managed to sand and fill these to a passable standard. One area of the ceiling he stopped short of finishing and came back the next day to finish, the join looks so bad! I questioned him at the time but he assured me that when painted you wouldn’t see anything after a light sand. He also advised me to lightly sand everything before painting which I thought was a bad idea! Help! What can I do to fix this? I’m planning to speak to him on Monday about my concerns but unfortunately I have paid him already. Thanks for the replies. I have had a recommended plasterer have a look today and he said it may be too heavy to have another ceiling skim as it’s been done twice now. I have spoken to the original plasterer and he has offered to spend the day filling with easy fill and sanding to make good. I’m not sure if I should let him incase it makes it worse. Would a decorator be able to improve it?

Are you a tradesperson and able to answer this question?

4 Answers

Jenksey

Rating: 5 out of 5
Tiverton
Scape surface pva 2 coats and plaster over but get a good man to do it right
Answered4 October 2020
3

Anonymous user

Hi I believe your best and cheapest way to solve it is find a good plaster on a day rate cause if priced no doubt will be high and get him to plaster two coats over the ceiling or it can also be filled out with easy fill but if it's bad will require 2days work for a painter where as platerering it will be a days work but then have to get painted but much better outcome. And if your really not happy try get half your money back to cover the cost cause either way gonna have to pay put more money ( yes a good decorator will be able to solve this situation maybe not a good idea getting the same plasterer to do the job)
Answered5 October 2020
0

Coulsdon Construction

Rating: 5 out of 5
Coulsdon
Unfortunately I have to agree
Answered5 October 2020
0

Anonymous user

Over- board the ceiling and apply two coats plaster Skim to achieve the recommended standard
Answered9 October 2020
0