Anonymous user 03/03/2024 - 3.29 PM

Can you build a brick pier ontop of compacted crusher? its really compact and solid. or is till best to dig it out and use concrete pad? Only be a standalone brick pier 4ft high 450mm square. will be handing a gate of it also Thanks for any info

Are you a tradesperson and able to answer this question?

4 Answers

Anonymous user

When building any structure i always recommend to install a concrete foundation. even though sub base compacted it can still move and subside overtime especially when a lot of rain.
Answered15 April 2020
31

Anonymous user

Build any structure off a concrete pad in this case at least min 150 mm depth if pillar is 450mm square concrete pad needs to be 750mmx750mm width to spread load of pillar structure
Answered19 April 2020
1

Ashlar Stone

Rating: 5 out of 5
Torquay
You need at least 150mm depth of concrete for the foundation. Along with a minimum of 150 of clearance around the brickwork to ensure that there is an adequate 45 degree sheer point angle to the bottom of the concrete foundation.
Answered23 April 2020
0

Allan mckeich

No reviews yet

Alexandria
The foundation needs to be 150mm thick and a wide scarcement around the pillar.
Answered25 April 2020