Hi I am currently in the process of a complete bathroom refurbish. I have had conflicting advice around plumbing the bathroom and boarding. Currently walls are back to brick. We are moving the toilet slightly, adding a freestanding bath into a different position to the original bath, new sink once again in a different place to the original and adding a enclosed shower unit. Should I be planning to reboard the room first or have the pipe work rerouted? It’s a box room bathroom if that makes any difference Thanks in advanced!

Are you a tradesperson and able to answer this question?

6 Answers

ProperTcare

No reviews yet

Bristol
Hi L. Surely doing all pipes first would be much more sensible and easy. Hope this helps Raphael
Answered19 February 2020
5

D & R Property and Plumbing Maintenance

Rating: 4.9 out of 5
New Romney
first fix plumbing services ,then floor.
Answered19 February 2020
0

Job done home improvements ltd

Rating: 5 out of 5
Heanor
As everything is bare it’s always best to first fix all plumbing before plastering
Answered21 February 2020
0

LSA PLUMBING AND HEATING LTD

Rating: 5 out of 5
Bootle
I've always carried out 1st fix on the plumbing before the boarding as been completed. Keeps everything tidy instead of a load of pipework and fixings on show in your nice new bathroom
Answered22 February 2020
0

Brownstone Building Services Ltd

Rating: 5 out of 5
Royston
Hi 1st fix plumbing and electrical would normally be completed before boarding and skimming.
Answered22 February 2020
0

ADB Services UK Ltd

Rating: 4.9 out of 5
Moorgate, London
The person that’s doing the boarding should be the one making the decisions if you are unsure
Answered23 February 2020
0