How long is a quote valid
Anonymous user 15/03/2024 - 2.53 PM
Hi I am undergoing a major decoration project on my house several trades have been hired and came out to provide quotes. I like to get quotes a couple of months in advance for big jobs sometimes the tradesman are eager to start but sometimes the job I want doing is in the budgeting/ planning stage. Would getting quotes 4-6 months in advance make a tradesman lose interest would they be happy to wait
Are you a tradesperson and able to answer this question?
6 Answers
GWS Multi Trade Builders
Rating: 5 out of 5
As a Builder providing quotes for over 40 years quoting for work 4-6 months in advance is fine but if we were providing material and theres any doubt of an increase in the cost of material we would explain this to the customer and provide an estimate
Answered23 December 2019
16
Timothy David Interiors
Rating: 5 out of 5
It should not be a problem. But make clear these intentions to anyone quoting for the work, and if posting on here add the info in the job description
Answered25 December 2019
2
Kitchen,Bathroom&Building Services
Rating: 4.8 out of 5
If it's a Labour only quote 3 months if it's a material and labour quote 2 months has material prices go up all the time but to be fair the customer to say roughly how long he wants to work to start so you can budget in any price changes that may occur over the following month's
Answered25 December 2019
1
ALC Jobs
Rating: 4.7 out of 5
I think it is fair to ask for price for future works. I would give a labour cost valid but show customer breakdown of materials and again 2 weeks before start date and show if increased.
Answered4 January 2020
0
Oolite Developments Ltd
Rating: 5 out of 5
Personally, my labour quotes are valid 6 months however if materials are required then these costs are only valid for a month as that's what my supplier gives me. This would be made clear to the customer when the quote is emailed through,
Hope this helps
Sean.
Answered6 January 2020
0
DB MAINTENANCE WORKS LTD
Rating: 5 out of 5
Labour only quotes I give three months but if materials are to be supplied by us then I give two months because of price changes.
As long as there is clear communication at the start then it’s normally fine.
Answered12 May 2021