I am getting my kitchen floor screeded for levelling purposes so how long before we can put the units back in the kitchen or tiling on the floor done. Someone said we have to wait a while before this is done Is this correct ?
Are you a tradesperson and able to answer this question?
3 Answers
The odd job man property services
Rating: 4.4 out of 5
Evening
It depends on the thickness but you generally only have to wait 48hrs before carrying out any work
Hope this helps
Answered10 February 2019
0
Anonymous user
It depends from the thickness of the screed. The thinnest screed you can carry on with your work after 24h if the thickness is thicker than 4inch you have to leave the screed to breathe and dry up to a week before you do any work. This is the safest way to do.