Screed of floor

Anonymous user 28/02/2024 - 3.42 PM

I am getting my kitchen floor screeded for levelling purposes so how long before we can put the units back in the kitchen or tiling on the floor done. Someone said we have to wait a while before this is done Is this correct ?

Are you a tradesperson and able to answer this question?

3 Answers

The odd job man property services

Rating: 4.4 out of 5
Colchester
Evening It depends on the thickness but you generally only have to wait 48hrs before carrying out any work Hope this helps
Answered10 February 2019
0

Anonymous user

It depends from the thickness of the screed. The thinnest screed you can carry on with your work after 24h if the thickness is thicker than 4inch you have to leave the screed to breathe and dry up to a week before you do any work. This is the safest way to do.
Answered12 February 2019
0

a.rodi

Rating: 5 out of 5
Leeds
Hi,give it a week to cure and harden.
Answered15 March 2019
0