Ready to hire?
Post your job in minutes, browse real reviews and choose who to speak to.Post a jobNeed some tips or advice?
Ask a questionDriveways & Paving
how long does it take to dig out a driveway? an average driveway that can accomodate 2 cars. driveway mainy grass , but a small area with concrete about 10% of the driveway is concrete
Anonymous user 28/02/2024 - 2.47 PM
hiring somebody to do my driveway and i was told digging can be done in half a day
Are you a tradesperson and able to answer this question?
54 Answers
Anonymous user
If you're hiring someone to do it and they've told you half a day,(and i'm assuming they've seen the job and we haven't),why are you asking again on here?
I don't know much about driveways but half a day sounds pretty good going to me...............(depending on manpower of course of which again we don't know) :/
Just going to trot off to Ebay now and get myself a nice shiny new crystal ball........;)
Answered2 February 2012
14
GJC Carpentry
Rating: 5 out of 5
Hiya,
Firstly are you having brick pavers or tarmac ???? your guy needs to go down a fair depth to allow for hardcore , compacting and finnished layer. A good operator with decent machine should achive this in half a day !
Answered2 February 2012
9
Habitat Landscapes Ltd
Rating: 5 out of 5
If they are using a machine to dig then yes, half a day for a drive that size sounds about right. If they are on about hand digging it then i would estimate a day and a half for the dig. I would advise to check they are digging pout the right depths as well. A minimum of 400mm from finnished level should be excavated, allowing for 100 mm hardcore (could re use the concrete drive for this) then 200mm of m.o.t (crushed concrete with finnings) all this compacted down with a wacker plate and then a 100mm is left for sand and blocks. some times people only like to use 30mm of sand and most blocks are 50mm so the level could vary slightly. The most important part of a driveway is the depth of the sub base. If it is not thick enough the weight of cars driving on and off over time may move the blocks.
Answered2 February 2012
9
Roc builders
Rating: 5 out of 5
Possibly depending on skill of digger driver,how much labour and location of skip/grabber pile.Definetly in a day though.
Answered2 February 2012
7
Anonymous user
If the guys using a digger, you was told right.
Answered2 February 2012
6
Anonymous user
yes it could. pretty quick these diggers you know
Answered2 February 2012
6
Anonymous user
I would need one day to dig out 8inches, then lay terram and stone up, so digging out in half a day is possible
Answered2 February 2012
6
Anonymous user
That's true. Especially with a digger. Two men could get the drive dug out and hardcore laid in a day if materials and skip arrived that morning
Answered2 February 2012
5
Anonymous user
For the size of the driveway you have it would be very easily dug out and hardcored in a half day with an organised crew of course with a digger and a grab lorry ordered.
Answered2 November 2017
3
R smith general builders
Rating: 5 out of 5
Depending on thickness of the concrete and if the work is started early by a skilled machine driver it should be dug up and leveled between 1 and 2 and hardcore layer the same day
Answered5 February 2017
3
Anonymous user
I usually aim to be excavated and stoned in 1 day you need a good reliable grab wagon driver go bring the type 1and take away the waste all in one hit, also it depends on the digger driver for a two car driveway after breaking the concrete I would dig in 1 hour
Answered6 November 2014
3
Anonymous user
if they have a mini digger then yes ,dug out and grabbed in a day ,but all depends on thickness of concrete to be broken up access ect
Answered2 February 2012
3
AMBER PAVING LIMITED
Rating: 5 out of 5
Hi
Half a day to dig out with digger is possible for a organized crew..
Answered11 February 2012
3
Anonymous user
we could hand dig that size in a day with 3 men and lay compacted sub base. with a digger you would start laying same day total job to finish without any brickwork would take no longer than 3 days depending on levels
Answered15 March 2012
2
Anonymous user
With the right machinery and weather conditions we could do it 1 day taken the grass driveway down to 16 inches deep breaking out the concrete drive and using as hardcore addding 4 inches of hardcore compact with a heavy duty machine 8 Inches of m.o.t (crushed concrete with finnings) all this compacted down with heavy duty wacker plate thenc membrain sheeting and adding sharp sand compact with wacker at around 2 inches your paving should be at lest 50 mm thick for car traffic most important is the digging deep enough to allow base for hard standing allow use a membrane sheeting to stop any weed growth in future all driveway most have a Concrete Ending curbs to support paving at last all paving most be compact and filled with kill and dry sand to fill in any spaces or gaps
Answered18 October 2018
2
Anonymous user
On average we dig around 150 m2 a day including grab removal
Answered17 April 2016
2
Anonymous user
any good compainy should be able to do it in 1 day and put foundation in as well
Answered2 February 2012
2
Anonymous user
With a mini yes. half a day would fair time. It can save a lot time and labour
Answered13 September 2016
2
Anonymous user
Less than a full day, that's starting work at 8 in the morning
Answered8 October 2013
1
Lifetime driveways
Rating: 5 out of 5
This all depends on thickness of concrete and if it is reinforced but if it is the average size concrete 2-3 men starting at 8 o'clock and a machine it would be a mornings work and as we use grab lorry for our muckaway if they get to you on time should be all dug out and ready to type 1 by 12-1
Answered20 February 2017
1
Anonymous user
If you start a about 8 in the morning you be finished bye 5 in the afternoon depending on how thick the concrete is .
Answered27 April 2016
1
Anonymous user
Yes this very possible with a digget
Answered26 April 2016
1
Anonymous user
Yeah i agree with most of these people if everything runs smoothly i'd get it doug out and stones up one day starting about 8 and be done by 4
Answered10 February 2015
1
Anonymous user
Would have to see the job before letting you know the time taken to excavate
Answered16 January 2024
0
JK Contractors
Rating: 4.9 out of 5
A area at that size with a digger driver who knows what he is doing should have the area dug up and at the right depth and based with a rough level in a day .
Answered12 April 2019
0
Anonymous user
I have a mini digger and it digs out in a day just make sure to dig down to the right depth otherwise don’t do the job it should be done right and should only be done once
Answered6 October 2019
0
Leo Stenson and Sons.
Rating: 4.7 out of 5
I use hand dig, wheelbarrow,2 men and Grab wagon= Half day to dig and stone-up!
CHEAPER for customer that way! No underground pipes damaged!
More work for me!
Answered19 October 2019
0
Anonymous user
All depends on thickness ov concrete and how easy it cums up but shouldn’t be no more than a day and depends on how many pair ov hands there is
Answered14 March 2019
0
Anonymous user
If you are using a digger then a half a day sounds right, by hand 2 days make sure they are digging the right depth.
Answered3 November 2020
0
City paving wales ltd
Rating: 3.4 out of 5
Half a day to a day depending on conditions
Answered2 October 2021
0
Anonymous user
Half a day is a good amount of time to complete the works.
We aim to have a driveway of that size excavated and base aggregate installed within the same day.
Answered20 January 2022
0
Anonymous user
Half a day using the right equipment
Answered23 October 2022
0
Anonymous user
A day to half a day depending on conditions.
Answered5 January 2023
0
Thomas Driveways & Landscaping
Rating: 5 out of 5
Yes this can 100% be done
Answered6 January 2023
0
Anonymous user
Hello there
In my opinion depending on the conditions and the equipment used eg. Digger and dumper, or if it’s hand dug and wheelbarrowed to the skip, it should be fair to say that it can be dug out anywhere in between half a day and a day and a half.
Answered4 February 2023
0
Brookside drives & patios
Rating: 5 out of 5
Depends what's underneath the ground and the access of the digging
Answered21 July 2023
0
Anonymous user
Should dig out and hardcore within the 1st day
Answered18 September 2023
0
Anonymous user
With a digger yes everything can be excavated all rubbish removed by wagon and install new type 1 mot lime stone hardcore and compacted
Answered9 January 2024
0
Your choice driveways and patios
Rating: 5 out of 5
Firstly are you having brick pavers or tarmac your guy needs to go down a fair depth approximately 300 to 350mm to allow for hardcore , compacting and finnished layer. A good operator with decent machine should achive this in half a day
Answered21 November 2018
0
Anonymous user
It could be done depending on man power or if they are useing a digger
Answered8 November 2018
0
Anonymous user
If you Get a big company in then half a day seems about right to dig out a driveway some driveway company’s have got grab lorrys and mini diggers.
Answered24 October 2018
0
Anonymous user
If the driveway is only for 2 cars I would guess at 25-30m2. If the concrete is 10% of driveway this must just be a path. 1 man on a small 1.5 tonne digger could dig up this area to a depth of 250mm-300mm in a few hours. Piling it up within 5metres of the roadside for collection with grab lorry and would all go on in one load. So yes the driveway could be dug out correctly in this amount of time.
Answered31 July 2018
0
Anonymous user
Hi,
There is nothing to be concerned about as it is a pretty straight forward job to do with a mini digger. If you hire the right person they should make sure to ask you what depth you need and give you advice on how to remove the excess. Depending how many tons of waste you have a skip or a local grab hire service are the best options. In this instance i would suggest a grab hire service. Total time to dig out and get hardcore down is usually one day.
Answered20 June 2018
0
Anonymous user
With the right machinery and team You could dig it out and get the hardcore down easily
Answered28 May 2018
0
Anonymous user
Hi considering the size of your driveway a professional company could easily get it fully dug out within one day
Answered4 May 2018
0
JC Drives and Patios
Rating: 5 out of 5
1 day to dig it out seems about right if you have the correct equipment
Answered3 May 2018
0
Anonymous user
That driveway you have suggested would be dug off and the hardore in within one day .
Answered3 February 2018
0
A1 Property Care
Rating: 3.4 out of 5
About couple of hours digging and scraping if he's a good driver dug out and hardcored in a half day for an area that size.
Answered16 January 2018
0
Anonymous user
With the right machinery digger yes can be done in a day no problem if digging by hand then I would say about a day and a half hope this helps
Answered23 August 2017
0
Anonymous user
If it's roughly 60 sq metres to 80 then yes depending on if they're using a machine or how Manny guys there is harf a day is about right
Answered17 August 2017
0
Midlands Paving
Rating: 5 out of 5
Hi my team can have a 4 car drive dugout membrane and MOT type one In a day but at the most shouldn't take more than two days
Answered9 August 2017
0
Anonymous user
With the correct machinery this job could be done in half a day Although you would have to dig a fare dept for a hardcore foundation
Answered7 August 2017
0
Anonymous user
With the correct knowledge and the right machinery a day and half seems to be about right.
Answered11 April 2017
0
Anonymous user
All depends on thickness of concrete I have a tonne and a half digger with a pecker and that'll do most concrete fairly easy. 2 car car port I would of said a day depending on where your location is etc
Answered8 January 2015
0