Skip to main content

Ready to hire?

Post your job in minutes, browse real reviews and choose who to speak to.Post a job

Need some tips or advice?

Ask a question
Conversions

garage conversion does not comply with building reg's or architects drawings, what can i do?

Anonymous user 03/03/2024 - 2.44 PM

I paid the builder a 10% deposit before the job was commenced. I refused to pay balance at the end until i got a completion certificate. the building inspector was out and there are a number of basic things that the builder has done that are not in accordance with my architects drawings or building regulations. For example, the drawings required 100mm insulation board on the external walls, the bulider has only used 30mm. There are no trickle valves on the window installed, which are required by the buiilding reg's in Scotland. The builder has not latex skimmed the concrete floor. The job was a disaster throughout and there are other minor aspects I am not happy with. The inspector will not provide a completion certificate until rectified. I really dont want the same builder back on site; i'd rather get a reputable local tradesman to fix/finish the job. Do i need to offer the original builder the chance to rectify the job? If not, what if anything do I need to pay the original builder? He has not done the job as contracted.

Are you a tradesperson and able to answer this question?

11 Answers

Anonymous user

your in a tricky situation!!! if you really dont want the builder back i can understand, make sure he is not out of pocket, for example if he has paid for materials that are on the job that are correct pay him for these. you dont have to, just the moral thing to do. then contact a reputable builder and get your building works finished. hope this helps regards Joe Williams
Answered1 December 2011
2

Anonymous user

Unfortunately, even though you dont want the builder back you must give him the chance to rectify the works, and hold any money due until you have the completion certificate, and you are happy. The trickle vents can be retro fitted, the floor sounds easy enough to rectify. As for the insulation not up to standard, if its in the cavity, then you do have problems.
Answered1 December 2011
1

Phoenix Specialist Contractors Limited

Rating: 5 out of 5
Dunstable
There's nothing wrong with paying a small goodwill deposit if that's what you both agreed prior to commencement, it shows commitment on both sides. I'm surprised your builder didn't ask for stage payments as the work progressed though, but then you don't say the extent of the work only that it was a garage conversion (so presumably not a massive job). If the garage was converted (presumably from an existing outbuilding?) the builder should have upgraded the cavity insulation as part of the renovation work (whether 100mm is achievable on any existing walls you don't say) but any new external walls would need 100mm insulation as a matter of course (any builder knows this). Your builder can retro-fit trickle vents to the new windows - it's a simple job and the vents can be bought online - most companies I deal with these days fit trickle vents as standard though, so where did your guy get your windows from? Is the concrete on the floor that rough that it needs latexing, or has he just left the oversite exposed and not bothered screeding the floor? What did your drawings show? Has the floor been screeded, and then walked/worked on before it's cured properly, and then simply broken up? As for getting it finished, you should at least give the guy the opportunity to put the work right. If he can't or won't then you'll have no choice but to use other contractors and deduct their bills from any monies outstanding to him. Did you sign a contract with your builder, if so there should be an arbitration process descibed in the contract. All the problems you've described should be simple fixes for your builder. The thought of getting the outstanding 90% should be motivating enough for him to sort them out for you, but there's plenty of capable tradesmen on mybuilder that will be able to get it done if he doesn't come through for you. Good luck Damon Smith D S Interior Services Limited
Answered1 December 2011
1

Anonymous user

it depend did you and the builder agree a written pre-start contract? you could say to the builder if you have no agreement you will get a quote to put all the snags right and take it off the final completion payment, he probably wont want to complete the job anyway
Answered1 December 2011
1

Anonymous user

if you are satisfied by the work carried out by the builder and depending if the work was to a gd standard by the building inspector spec then yes. but if the building inspector does not rate the work he has done why offer him the work again to potetialy mess up. if i was not satisfied by the work i would not pay him and give him evidence of the building inspector showing that is did not meet regs and the poor work quality stated by the building inspector.
Answered1 December 2011
0

Roc builders

Rating: 5 out of 5
Harlow
In your current situation,your conversion isnt worth a penny.Without completion from building control,all you have is a fancy unusable garage.The window problem is an easy fix,the insulation another problem altogether.Im presuming as you are after completion,all the walls are plastered etc and you have had to make a hole in the wall to show the building inspector the insulation that has been used? If so,why have you allowed this idiot to plough through the work without ensuring that certain things were checked before they were covered up? Hopefully the foundation for the door infill has been passed as it is unlikely to be suitable if he skipped the inspection on this too.Personally i would not entertain this fool again.Post this as a job on here and let someone who actually knows what they are doing take a look.Hopefully the money you have retained will cover sorting this out though i very much doubt it.One more thing.You get what you pay for in this game and if this guy was the cheapest at quote stage,he will definetly end up costing you more than a quality tradesmen by the time you have sorted his corner cutting.Hopefully other job posters will learn from this.Cheap jobs usually end in tears.
Answered1 December 2011
0

Anonymous user

Hi, If the job has not been completed to building regulations and your own personal satisfaction then you could offer the builder one chance to rectify his mistakes and bring them up to standard. If he does not carry this out then you should not pay the builder and use the money to pay a reputable builder to come and rectify and complete the works.
Answered1 December 2011
0

W Lee Carpentry Limited

Rating: 5 out of 5
Northampton
Hello. Not sure where to start really. In England it is the home owners responsibility to make sure the work carried out on there property is up to the building regs standard ( not sure about Scotland). It is unfair I know as you have employed a builder to make sure this happens and quite obviously he has not.In the interest of fairness I would give the builder a chance to rectify his work with a very close eye being kept on him with photos being taken along the way. But if communication and or trust has broken down I would write to him and state that because he failed to meet the building regs required and it is now going to cost XXX amount of pounds to put right recommend that he walks away or you will seek costs from him to to rectify his work if he continues to ask for money from you.I am presuming you have had a detailed quote from him and not a verbal agreement. As a verbal agreement can undermine your position greatly. If I can help any further please do not hesitate to contact me. If you would like a sample quote to see what you should be looking for again please do not hesitate to ask. Wesley Lee W Lee Carpentry Ltd
Answered1 December 2011
0

Anonymous user

yes you would be obliged to ask the builder to rectify his work give him a time scale to do the work as stated on the achitects drawings if not completed in that time, you are entitled to get someone else, shame i am not near you or i would have put the work right for you. if he does put the work right then you would have to pay him what is owed to him taking into account the inconvenience if you can get somthing knock of the original price.
Answered1 December 2011
0

Anonymous user

hi there all the convertions i have done in scotland all floors have to be insulated even if that means raising floor above house floor reinsulating the out side wall should be an easy fix as long as new wall does not not come over edge of window if this is the case then he has to narrow window you should give him the chance to fix the problems as you probably still have to pay him aprox £5400 it wouldnt cost this to put it right im not sticking up for him if he has to reduce the width of the window then this is why he used the wrong thickness of insulation and hoped building control wouldt notice hope this helps neil
Answered7 February 2012
0

REECE BUILDERS LIMITED

Rating: 5 out of 5
Rochester
Hi not quite sure about some of the answers your getting Simple If the builder is unaware of the building regulations requirements all he has to do is ask the (BCO )Building control officer He will tell him what is required with regards to insulation He then calls the BCO back at certain stages to have a look and insulation is one of them stages the BCO then ticks that stage of The BCO is not there to assure if the guy is a tidy or good builder just that it’s to standard It’s not your responsibility to make sure your builder does a good job and take pictures of him it’s the builders responsibility to make sure he does it correctly end of storey Give the guy a chance to correct his works and if he refuses then don’t pay him get another builder The price difference between 30 mm and 100mm insulation board is quite a lot so either he was trying to cut corners to save money or he just didn’t know any better I think he just didn’t know because if the BCO had of been called back when he should have he would have told the builder there and then that the insulation was inadequate Hope it all works out for you
Answered15 December 2020
0