Removing carpets and tiling living and dining room

Anonymous user 09/03/2024 - 2.44 PM

Hi, We are moving into a house with old carpets in living and dining rooms? We want to use ceramic tiles instead of new carpets. How long does it take to tile the rooms....41 square meters.It is for the lounge and dining room. Thanks

Are you a tradesperson and able to answer this question?

2 Answers

Anonymous user

So long as the substrate is ready to go and doesnt need any remedial work then it wouldn't take very long. Going on the assumption it would be a concrete substrate and ready to prime and go... 4 days in and out. Me & 1 labourer
Answered24 October 2016
1

Rory Adams

No reviews yet

Lowestoft
Hi it maximum I rekon it would take would be 4 days with 2 tilers 1labourer but we recently done a 60m2 floor in 2 days depend on how square rooms are amour of cuts ect but no longer than 4 days
Answered23 October 2016