How long to tile a bathroom floor 3sq.m.

Anonymous user 23/02/2024 - 3.05 PM

A very small bathroom in a new build house. 3sq.m. Job requires:- Temporary remove toilet and pedestal wash-hand basin. Remove plastic bath panel. Lift existing floor tiles and ply wood underneath. Fit new ply, and lay tiles. Re-fir toilet, pedestal wash-hand basin and bath panel. I've been quoted for 3 days. Previously had job done in one day, tiles down by early afternoon, and plumber returning at tea time to re-fit toilet etc. 3 days seems excessive.

Are you a tradesperson and able to answer this question?

2 Answers

Anonymous user

Hi I would say 1 day and a morning. First day I would remove Toilet ,Sink and bath panel. Then install new aqua panels or no more ply boards. Once that has been done I would expect to take the afternoon to Tile the floor. Respecting Drying times etc I would return the next day to grout silicone an fit accessories back in place. Adam Hope this helps you?
Answered14 October 2016
2

Anonymous user

First thing do not use ply use cement board not much difference in price ,just the tiling alone I could fit board and tile in a morning but would charge a day and as you say, fit sanitary ware in afternoon.
Answered14 October 2016