Anonymous user 28/02/2024 - 3.23 PM

We are looking to lay floor tiles to cover approx 40m2 (tile size 60cm x 40cm) and then also tile a medium sized bathroom with metro tiles as well as some metro tiling in the kicthen (behind sink and oven). Can anyone give a rough idea of timings? I've been quoted 2 men taking 3 weeks. To the untrained eye that seems excessive but i may be completely wrong. Thank you

Are you a tradesperson and able to answer this question?

5 Answers

Perfectly Finished

Rating: 5 out of 5
Godalming
Hi Your floor tiling will take 3 days, maximum. Your kitchen wall 1 day and your bathroom max 2 days......plus any preparation. 1 man!
Answered14 September 2016
3

Anonymous user

They must be going to sit around for two weeks,average 6 days one tiler.
Answered16 September 2016
3

CGL Refurbishments

Rating: 5 out of 5
Birmingham
Hello Danielle From the details that you provided I think that in one week everything can be done Hope this will help you
Answered14 September 2016
1

Premier Tiling Manchester

Rating: 5 out of 5
Manchester
Yes 3 weeks is excessive. But I would say this job would be rushed in a week.. if you want a tiler to take time and tile it to a high standard it may take a little longer. Absolute maximum 2 weeks though.
Answered20 October 2018
0