What is the main job of an architect

Would like to extend garage rebuild our utility room with a shower and toilet. But still have side access. how long to get permission if needed.

2 Answers

Generally you should allow 3 months for something simple like you have proposed, however check your local planning authority as some require more time. Once you have the permission you will then have 3 years to start the project.

Answered 19th May 2016

Architects Floors

Member since 19 May 2016

The planning permission itself would take 8-10 weeks for the Council to decide. An architect should usually take maximum 2 weeks to provide the drawings to you. So I would suggest the longest time from start to finish is 12 weeks.

Answered 18th Aug 2016

Richardson Architectural Design

Member since 17 Aug 2016

Need help with your project?

We have tradesmen ready to help you. Post a job, read reviews and hire today.

Post a job

Need some help?

Post a job on MyBuilder to find quality, local Architectural Designers who can help you with your project.

Search all questions