do I need to obtain any surveys or reports to have a chimney breast removed?

Anonymous user 03/03/2024 - 2.41 PM

Are you a tradesperson and able to answer this question?

4 Answers

Anonymous user

As its structural works, you need to inform bco.
Answered12 October 2011
1

Anonymous user

It is really a building control job as you are involving structural work. It can be done on what's known as a building notice. Even with that you still need a structural engineer to design the supports. Hope this helps? Most people don't realise this work comes under building control. Shaun
Answered12 October 2011
1

NSD BUILDING SERVICES

Rating: 5 out of 5
Dereham
We have recently taking down a large chimney(top/bottom) and had to have a structual engineer and building regs an experienced builder will inform you of what is required hope this helps
Answered12 October 2011
1

Damp Shield Preservations LTD

Rating: 5 out of 5
Salford
damp tech preservations i have carried out loads of this type work building controls will be involved in which you will need a structural engineer first to draw plans on load bearing lintels when your buider has worked to plan thats when it will be re-inspected by building controls hope this helps mr woods
Answered13 October 2011