hi im doing a office brick built and I would like to no how much ballast and cement to use in foundation at 450 wide 6 mertres long and 4.5 long at a depth of 300 mm for concrete please

Are you a tradesperson and able to answer this question?

2 Answers

HD Design and Build

Rating: 5 out of 5
Herne Bay
Get it ready mix! knocking it up yourself is much more expensive
Answered10 February 2015
0

Terry Owen Carpentry

Rating: 5 out of 5
Swanley
Is the 6m x 450mm x 300mm one side of the strip foundation and the 4.5m x 450 x 300mm one end. if so the calculation is 6 x 0.450 x 0.300 x 2 = 1.215 cubic metres of concrete. 4.5 x 0.450 x 0.300 x 2 = 1.62 cubic metres of concrete. 1.215 + 1.62 = 2.835 cubic metres of concrete required for all 4 sides of the foundation. Get onto a ready mix company and ask for 3 cubic metres of concrete your job specification should tell what type of mix you need. Good luck Terry owen
Answered12 February 2015