What are the rules and requirements for adding a new soil pipe for the purpose of installing a cloakroom to a redundant boiler cupboard?

Anonymous user 03/03/2024 - 2.38 PM

Foul drain runs back to front past the point where the soil pipe would be installed

Are you a tradesperson and able to answer this question?

2 Answers

Affordable construction

Rating: 5 out of 5
Waterlooville
Hi you need to inform building control,and make planning aware of change of use of the room, then install a stub stack if your upstairs toilet is already vented with an exsisting soil stack , a stub stack is all you wold require ,exit though your walling and dig to nearest drain /manhole , and connect at benching level , put on test and then get building control to inspect and pass.
Answered26 October 2011
1

Anonymous user

You would be best to talk to your local planning department as you may need permission to do so, and would probably need to be tested also. Its best to go through the stages as it keeps your paperwork right if you ever decide to sell the property on. Kind Regards Andy
Answered30 August 2011
0