Skip to main content

Ready to hire?

Post your job in minutes, browse real reviews and choose who to speak to.Post a job

Need some tips or advice?

Ask a question
Bathroom Fitting

How long should a job take?

Anonymous user 01/03/2024 - 2.38 PM

Currently i have an 8ft x 9ft bathroom, with bath, hand basin and loo, Walls are tiled. I wish to put in a new bath, seperate shower, loo and hand basin. more or less in same position, Now i have had two quotes and both to me seem high as its on labour only basis, but what stikes me more is both said would take minimum of 2 weeks to do the job. I freely admit im no expert but in my head i cant see how it can take 10+ days, Day 1 just remove bath. loo hand basin. Day 2. remove tiles and bring back to brick work, Day 3. Dry line walls Days 4, 5 6 plumb Day 7 plaster Day 8 fit fixtures Day 9 10 tile 16sqm2 Now as i say im no expert and dont begrudge if they are right, but i fail to see how it can take a whole day to remove a bath, hand basin and loo, as to me after i have turned off the water supply, i would cut the pipes and just remove. no more than 2 hour job at the most.... Am i thinking right or does it really take a day to remove current fixtures and then 3 days to plumb in a 8ft x 9ft bathroom? Wanted to add this is 2 men working, both quotes 2 man job which leaves me asking this question. Opinions welcome please thanks very much. Thank you all for such a response, has helped me a lot, My last question as some of you have pointed out is the men are wanting to take the current tiles off and plaster off underneath that, so on three sides its back to brickwork. Now from that brickwork they wish to put up plaster baord, and i belive plaster and tile over that. That is my full understanding. Strip back plasterboard plaster tile Some of you have pointed out not all this work is required, So can i ask why would they quote to do it if not required is it a belt and braces exercise or just work for doing work Thank you all for all responses Mart

Are you a tradesperson and able to answer this question?

13 Answers

CW Domestic Plumbing

Rating: 5 out of 5
Newcastle, Staffordshire
Hi Im a sole trader and have worked on my own all my working life after my training. I fit bathrooms every week to high sandards. I do everything except i use electricians and plasterers if needed. All this talk of 2 week for 2 men makes me laugh. I fit a full bathroom with 23sqm of wall tiles and a 7sqm tiled floor in no more than 7 days working 8am till 6pm. I class thats as an avarage bathroom. And why would you plaster boarded wallls that are going to be tiled, it will only delay a job futher. Regarding you latest question- If when your tiles are removed and the wall is in a bad state then the best option is to strip them back and do a dry line.I always use moisture boards in bathrooms or better still tile backer boards. If you are fully tiling the bathroom then there really is no need to plaster over the new boards just seal them with a waterproof PVA and you will have a good surface to tile too.
Answered19 February 2026
65

Anonymous user

i have just completed a new bathroom with my stepfather. we are both multi skilled builders and it took 8 days to complete. bear in mind we were on a price and not day work and it was a complete refit included decorating. we worked on average from about 8.30 til 5.30 with 1 break when we were hungry. we produced a high quality finish but could have completed the job in maybe 7 days if we had thrown it together. we also removed and refitted the toilet and sink daily to enable customers to wash as normal and use toilet within reason. we had the shower cubicle in use after 4/5 days so this lack of room slowed us down but always with the customer in mind. maybe if we had said go shower or toilet in the garden we could have done it in 5 days but why are you so bothered if it takes 10 days??? if they are on a price then it shouldnt matter how long it takes, within reason. 10 days should be the maximum though for any bathroom.
Answered21 August 2011
27

Anonymous user

Hi Does seem a bit excessive, however perhaps they are allowing themselves a couple of days to cover any unexpected problems or delays. If they say 2 weeks and it only takes one, then you are happy. If on the other hand they quote 1 week and it takes 2 then you are not a happy customer. Regards Malcolm MJM Plumbing Services
Answered5 August 2011
20

Anonymous user

Hi You wouldn't normally, strip plaster back to brickwork (unless the plaster is falling off the walls), then dry line, then plaster and tile...you can tile on dry lining. You normally dry line because the walls are not upright, which tends to show in the tile cuts at the end... I don't feel they have allocated their time properly. I think they are pricing for a high finish quality, but you certainly don't need too plaster the tiled areas. Most of it is a one man job, so I cant see how they price for 2 men for 10 days plus... Get a few more quotes, if they all say 10 days...it probably about right.
Answered9 August 2011
19

Anonymous user

Hi there, this is a typical 5 day job. Our company would charge labour only at 2 fitters on £180 per day each. No other trades would be required unless you needed electric work and then we would use a Napit certified electrician, his fee would be additional. First day strip out and start on first fix of pipework. Second day, remainder of pipe and wastes. Third and fourth tiling/grouting, (bath installed) Fiifth day, final fit.
Answered5 August 2011
19

Aztec Bathrooms

Rating: 5 out of 5
Morpeth
The quote for time you have received is probably not too far off. It depends how many men can get into the bathroom at any one time Day 1. Remove suite, tiles, take back to brickwork Day 2 and 3. First fix plumbing Day 4 Dry line walls Day 5 Plastering Weekend ? Let it dry, you shouldn't tile onto new plaster whilst its drying Day 6 and 7 Tiling - must let tiles set before grouting Day 8 Grouting Day 9 and 10 Second fix plumbing and suite installation You should be reassured that the quote you have takes this long, they seem to want to give you a proper job. If you get a quote saying they can do it in less time than this, I would suggest that the trademen are more concerned with getting paid as soon as possible, and not with giving the best job possible. Hope this helps
Answered5 August 2011
16

Anonymous user

Hi this dose seem a bit excessive, especially for 2 men. Are the walls that bad that they need dry lining & plastering? If you are tiling? Tiling should be done about day 4 before you fit basin ETC. I would say 10 day yes But 1 man But 2 men 6/7 days max. Hope this helps. Chris.
Answered5 August 2011
12

Anonymous user

From the information you have given i would be charging you around 3.5k labour and would require 10 working days for completion.I dont think your contractors have explained there time very well,or in the correct order.You havent mentioned electrics or decorating,are these included? Remember these are only quotes,you are under no obligation to commit yourself to anything until you are entirely happy.
Answered5 August 2011
11

Anonymous user

Hi, I Have been installing bathrooms for over 10 years, & on average a complete bathroom replacement will take 2 weeks. I agree it does not take all day to remove a bath & a w/c- however if you have no stop cocks to switch off the hot & cold water supplies, it does take time to drain down the water system before you can start- then install new stop cocks & then re-fill your system & remove air locks etc. There are many such problems that do arise when taking on a full refit. Why not ask for daily rate figures & you can watch & see what they are doing all day? Hope that helps G
Answered5 August 2011
8

W Lee Carpentry Limited

Rating: 5 out of 5
Northampton
Hello. This does seem excessive. This job should only take 6 days 7 if there is any problems which occasionally do happen. I would reccomend getting a few more quotes. Wesley lee W lee carpentry ltd
Answered5 August 2011
8

Anonymous user

its hard to say exactly how long it will take to do the job untill you actually start it. without seeing the job its hard to say how long it should take. we do bathrooms in 3 days or 3 weeks all depends on what you have to do and is it just a straight swap with all the pipe their to use.
Answered5 August 2011
6

Steve Rolt Home Improvements Ltd

Rating: 5 out of 5
Buntingford
8-10 days for an average size bathroom
Answered13 October 2017
4

Anonymous user

2 weeks for 2 blokes does seem excessive, but we haven't seen the job & exactly whats required. If 1 quote said a few days & the other said 2 weeks - then I'd query what the differences were... But if 2 different fitters have seen the job & have both suggested approx 2weeks - then I'd guess they are basing there timescales on the information they've seen, plans, info, spec, work involved etc. Get another quote and see what they say... PS. don't bother plastering the areas that are going to be tiled. I'd presume only the ceiling actually needs tiling
Answered6 August 2011
3