How do i mix off white wet dash harling? my brother says chips, sand, snowcrete and little lime but i am unsure as of how much of each i should use. Any help will be much appreciated.
Anonymous user 03/03/2024 - 2.30 PM
Are you a tradesperson and able to answer this question?
3 Answers
Anonymous user
first coat 2 plastering sand 1 sharp sand 1 cement,don't incorporate waterproofer in this coat, rule and leave with a combed finish ready for second coat.
second coat 2 chips 2 sand 1 snowcrete 1 lime mix together to achieve a mix similar to very wet concrete,then apply using a small coal shovel flatten sides of shovel to get better spread, put waterproofer in top coat as with a wet dash/ slopdash you need suction when applying the top coat in order that it doesn't slip
Answered25 February 2011
9
Anonymous user
first coat 3 rendering sands ( not yellow building sands) 1 lime 1 snowcrete
second coat 4-1-1 apply stone chipping to wet render (apply wet chipping)
Answered25 February 2011
7
Anonymous user
hi alan,i usally do a scratch as normal without waterproofer let cure for two days.second coat render smooth then flick on yer chippings.ratios two chips,two sand,one snowcrete,one lime.lightly flattern with tile pad.good luck.
Answered6 March 2011
5