Hire a tradesperson!

Our tradespeople are ready to help. Post a job for free, read reviews and hire today.

Need some tips or advise?

Extensions

Should we have seen the structural engineers report (pillars on each side of kitchen)?

Anonymous user 3 March 2024 - 3.06 PM

Can anyone help please. We recently had an extension built, we extended the kitchen and the original external wall was removed, we wanted to keep pillars at the walls to a minimum and the builder said no problem. When we travelled over to check on the house, we had huge pillars on each side of the kitchen where the steel was sitting. When we asked the builder he said the structural engineer had requested them? We have seen nothing of a structural engineers report and we don't know if we should have? Also does anyone know if we should have any sort of certificate for the electrics that have been done? Thank you.

Are you a tradesperson and able to answer this question?

4 Answers

Anonymous user

I am a structural engineer myself and get asked this question a lot. Pillars aren't required, but the cost implications are huge. The reason Pillars are required in your case could have been for a number of reasons... 1. To avoid party wall issues on joint foundations (may not be relevant) 2. If the pillars where removed the existing foundations would have to be upgraded (huge costs) 3. If the opening was bigger, the loadings at the beam bearings could have to high for the existing masonry. It is possible to remove pillars but the cost is high, 99% of the time leading to foundation works and you will have to put in a whole steel frame to deal with lateral loading. You could always check with the engineers drawings and see if they concur with what you have, but it sounds like your builder was probably following the structural engineers orders
Answered12 May 2016
2

S.J.Brickwork
Rating: 5 out of 55529 reviews
Tavistock
As builders we are bound by architects engineers and building control and as so your architect or building control should have your engineers calculations as to how big your piers should be you could ask them for the calculations if you cant ask the engineer direct
Answered29 March 2014
1

kevin cassidy building contractors
Rating: 5 out of 55555 reviews
Accrington
You should always receive an electrical certificate for alterations to your electrical system. Minor works certificate as a minimum for altered circuits and electrical installation certificate for new circuits which are also notifiable works(require registering with local authority borough council) REF:Pillars, Steels generally sit on pillars but to see if this was avoidable you would need to discuss this with a structural engineer.
Answered29 March 2014
0

AJ Plastering & Building Services
Rating: 4.9 out of 54.9545 reviews
Bradford
A structural surveyor should have specified size of steel, or at least building control officer agreeing with builders calculations if he is experienced in adding steel etc. check
Answered29 March 2014
0