Anonymous user 28/02/2024 - 3.00 PM

Hello! We are having the bathroom totally refurbished with a new bath, shower & basin, including gas piping refitted, plumbing, plastering etc. Can you please advise if the above order of work to be carried out is correct? Many Thanks

Are you a tradesperson and able to answer this question?

1 Answer

AD Building and Maintenance

Rating: 5 out of 5
Boston
There is a sequence of events in doing any refurbishment work, but let's assume the room is empty, first put all your services in, pipes, waste etc in the correct places to enable once tiled your fittings to be placed and plumbed in. Trying to to make sure that all pipes when laid have been pressure tested and checked for leaks as after being tiled it is a more expensive job to put right. Good luck. Tony
Answered11 January 2014