When does the fuse box get replaced for a house rewire?

Anonymous user 01/03/2024 - 2.48 PM

Looking to get my 3 bed house rewired. I understand there is a first fix and second fix. When does the fuse box get replaced, 1st or 2nd fix? Is it standard to get telephone points done as part of rewire? Should I be expected to make a payment after first fix? Thank you.

Are you a tradesperson and able to answer this question?

4 Answers

Electrical Safety Services

Rating: 5 out of 5
Dereham
The new consumer unit is normally one of the last things to be fitted and comes in with the second fixing. Once in place the installation testing is completed, (e.g. RCD testing, Earth Fault Loop Impedance testing etc) and the results recorded on the schedule of test results which should be given to you as part of the Electrical Installation Certificate for the completed job. If possible ask your electrician to supply a decent UK brand of consumer unit, MK, Wylex, Crabtree etc as there are a lot of flimsy Chinese ones around that are very cheap and poor quality compared to the UK brands.
Answered25 June 2013
4

Anonymous user

Dear Candy, the consumer unit is generally replaced as part of the 2nd fix, but circumstances may change this. If the property is going to be unoccupied when the work is carried out then the electrical contractor will decide the best time to do this, as he / she may require it to facilitate any additional circuits etc. Normally the upstairs lighting is replaced first & reconnected temporary & safely to allow lighting to still operate. Then floor boards (or what routes are decided) are lifted / routed to allow the downstairs lighting & upstairs power to be replaced, (again depends on circumstances). This then reconnected temporary & safely if required. The last area is downstairs power, but depending on floors / routes this may be included in upstair's work. The final works, earthling / main bonding alterations at mains etc can be addressed. However if you are still occupying the property, why this work is being progressed, then there are times when you must be left with some lighting & power for safety reasons & convenience. If you discuss this with the electrician, you can then agree a programme. Regarding data / telephone outlets/ TV aerial, these can be installed as other works are being carried out. Scheduled payments can be agreed as work is progressed & I would again agree % payments. If the house is unoccupied then no more than 60% after 1st fix & remainder after 2nd fix / final including certification. If the property is occupied while work is carried out, then multi payments of say 20% while work is being carried out at your agreed stages. Hope this helps, regards Peter
Answered20 June 2013
1

V.A.Electrical services

Rating: 4.6 out of 5
Derby
I always take 3 payments when do full rewiring. First before work starts to cover cost of materials. ( 30% ), second after first fix and last when job completed. First thing is to do temporary power point(s) and same time upgrade earthing and I start install consumer unit as part of first fix. About TV or phone points, its should be in contract which one has jobs description. Vadims www.vaelectrical.co.uk
Answered22 June 2013
0

Anonymous user

I agree, I work in the same way 1. pay for parts, 2. pay 1st fix, 3. pay when job fully signed off. Word of warning, I would suggest rcbo to be fitted which is better than the dual rcd boards that could plunge the house into darkness when they trip. A rcbo board would only allow the affected circuit to be affected. Make sure you don't just get given a certificate but that the work is fully certified with a scheme and building compliance is generated, a warranty should be available.
Answered23 July 2013
0