Can anyone suggest when the best time to get a shower fitted. We have two old bathrooms, currently without showers, that we've just started to renovate - is it best to get the shower fitted as the first or last job in the project?
Are you a tradesperson and able to answer this question?
5 Answers
A.J Plastering and Tiling
Rating: 5 out of 5
Hi There,
The pipework and or electrics would need to in place before tiling, and the new shower units fitted once tiling complete.
Regards
Tony
Answered15 March 2011
3
Anonymous user
Plumbing pipework first, Then shower tray , then tile. Next shower valve and rose, then shower enclosure.
Hope this gives you an idea.
Answered15 March 2011
1
Anonymous user
hi there, when doing a bathroom refurb weather it be installing a shower or bath, i would always get the room totaly gutted, new pipework put in place then install bath or shower tray only then fully tile, the reason i do this is so you can tile the bath or shower tray into the wall and make it more water tight. you would have a problem if tiled first as the chances of the walls being square are not very good and with a shower tray being square it wouldnt fit tight, and you would be left with big mastic joints.
As for the shower screen and shower itself i would fit that after tiling, grouting and polishing has taken place. hope this is of any help.
kind regards
Answered15 March 2011
1
Anonymous user
The first fixing (plumbing and electric) needed first .After this you can do the tiling and second fixing of plumbing and electrics.
Elio
Answered16 March 2011
1
Anonymous user
Hi
You need to run your pipes (first fix), fit your shower base, seal, then tile and fit your shower unit etc.
Answered16 March 2011