We figured out that we would like to get the following done for our lounge and dining room.
1.Replace the carpets with solid wood floor(DIY)
2.Skim/replace the artex ceiling and fix flush ceiling lights(tradesman)
3.Strip wall paper and paint the wall(DIY)
What would be the best sequence to do these work.
Anu suggestions/tips to reduce the cost,speed up the work,get desired looks

2 Answers from MyBuilder Painters & Decorators

Best Answer

Geoff has answered the question for you,Gary

2012-11-08T12:20:01+00:00

Answered 8th Nov 2012

Hey this would be what I would recommend:

1. Rip out carpets and gripper rods.
2. Start stripping paper.
3. Get ceiling skimmed.
4. Fit spot lights.
5. Decorate room.
6. Fit flooring and beading.

I hope this helps.

Regards,
Geoff

2012-11-05T18:05:02+00:00

Answered 5th Nov 2012

Post your job to find high quality tradesmen and get free quotes