Lead flashing

Hi

Looking to had flashing put on rear addition. Option 1 sounds a thorough job. But is Option 2 ok as well?

Option 1
Remove top row of tiles and cement flashing to back addition wall. Lay new tiles where necessary, fit new 300mm Code4 lead flashing and re-point lead work with a 3 sand and 1 cement mortar mix.

Option 2
Lay 300mm Code4 lead flashing over existing cement and tiles. Fit a galvanised stop-bead over lead-work and to wall then with a 3 sand and 1cement render to wall.

2 Answers

Option 1 - Sounds like the correct way to do the job

Option 2 - Sounds like Heath Robinson's way of doing things

http://en.wikipedia.org/wiki/W._Heath_Robinson

It is not recommeded to point lead with mortar as it cracks over time .

I would suggest you use this or similar

http://compare.ebay.co.uk/like/360214608957?var=lv&ltyp=AllFixedPriceItemTypes&var=sbar&adtype=pla

Answered 29th May 2012

SBS Ltd

Member since 23 May 2012

option 2 is the cheap/cowboy option yeeeeeeeeeeeeeee hahhhhhhhhhhhhh ,remember and feed his horse some hay .ride em cowboy

Answered 29th May 2012

substructure

Member since 7 Jun 2008

Need help with your project?

We have tradesmen ready to help you. Post a job, read reviews and hire today.

Post a job

Need some help?

Post a job on MyBuilder to find quality, local Roofers who can help you with your project.

Search all questions