Development plannning and, planning permission cost and validity

Hello everyone,

I have read a lot of questions and answers on this forum and they're very useful but they don't answer some of my questions.

1) If a plan is drawn for 2 storey extension and fences next to a footpath and the planning is approved. Can you do both the jobs at different times such as extension this year and the fences next year or so?

2) Is there a validity period for planning permission that is approved? For example, if the planning is approved and the work has to be carried out within 2 years?

We are from Yorkshire, if this helps in anyway.

Thank you

2 Answers

Hi, the answer is yes to both questions. You can do the work in stages and work has to start within 3 years from the date of the planning approval. Regards, Steve

Answered 16th Jun 2016

HousePlans

Member since 3 Jun 2016

No feedback

Once you have obtained planning permission you have 3 years, from the date of the approval, to start the work. Once you have started the work, which is presuming you have Building Regulations approval in place, and the Local Authority have carried out a commencement inspection, the application will last indefinitely.

Answered 18th Jun 2016

White Agus Partnership

Member since 28 Feb 2014

Need help with your project?

We have tradesmen ready to help you. Post a job, read reviews and hire today.

Post a job

Need some help?

Post a job on MyBuilder to find quality, local Architectural Designers who can help you with your project.

Search all questions