Hire a tradesperson!

Post your job for free and without obligation
More than 226582 connected tradespeople
Over 2478826 verified reviews
Damp Proofing

How worried should I be about the timber joists and flooring in a new extension touching the wall below the dpc?

Anonymous user 11 September 2011 - 4.00 AM

I'm having a single storey extension built (approx 4m x 5.8m). The builder inserted the air bricks and dpc too high which meant that, when he put in the floor joists (hung off ledger boards bolted directly to the blockwork), the ledger boards covered the air bricks and all the timbers were below the dpc. He admitted this was wrong when I pointed out to him that this couldn't possibly be right. They have now put in new air bricks lower down so they vent underneath the floor joists. With the dpc the builder suggested either injecting a dpc lower down or inserting a length of damp proof membrane between the ledger boards and the wall. I sought advice from a surveyor friend who said that neither of these options was acceptable (the injection system isn't that reliable and adding a membrane between the timber and walls was flawed because every bolt hole would puncture the membrane and allow damp through the hole). He said the ledger boards should be scrapped and the joists should be hung from the blockwork using S type joist hangers so that at no point does any wood touch the walls below the dpc. This is what the builder has now done. However, the joists are so tight in the hangers that some still touch the blockwork and none of them are more than 1-2mm away from the blockwork. How worried should I be over this? What's the minimum gap you would recommend between the wall and the joists? And between the wall and the floorboards themselves (as they will also be below the dpc)? Would a solution be to build a sleeper wall (with dpc and wall plate) at each end and rest the floor joists on this so that they are not connected to the blockwork at all? As the sleeper walls will then be taking the full weight of the floor, do they need some sort of foundation or can they just be built directly onto the oversite concrete? I'd be really grateful for any advice please. P.S. I'm on the west coast of Scotland if that makes any difference in terms of building regs, etc. P.P.S. Before anyone else assumes I went for the cheapest dodgy builder, he's a well-established local firm, recommended by the architect & was main contractor on building works at a private school in the area!

15 Answers

Anonymous user

i would be more worried about getting final cert ,if this builder cannot get a simple thing like damp course level correct ,what other horrors are going to crop up through the build ,i gather he was the cheaper offer ,beware of cheap imitations ,said it a hundred times there are no bargains to be had in building good luck
Answered12 September 2011

Like

23

Anonymous user

Sounds like your builder made a big mistake, you shouldnt get the dpc and floor levels wrong. However, if you go down the route of sleeper walls, then you will need some decent foundations for them. An alternative, as he has now fitted hangers, you can either get joist end caps, used as if they were built in, or wrap the ends in dpc, both prior to fitting into hangers.
Answered14 September 2011

Like

19

Anonymous user

Sleeper wall, maybe best. Joist need to be kept off the wall, it's a bit bodgy though
Answered15 September 2011

Like

13

Anonymous user

Best option is right first time.dpc 150 above FINISHED ground level.That is the regs and any arc would put that an plans.Get it put right now save you loads of problems later.Leave existing damp in place,get a good brickie to install a new one lower even if you use a sleeper wall you will still get rising damp
Answered18 August 2012

Like

12

Anonymous user

The other way is to take out the suspended floor, lay in damp proof membrane (lapped up to DPC height), sand blind it and put in concrete floor screed.
Answered19 October 2012

Like

11

RMD Planning
Rating: 5 out of 5551 review
Rainham
I would advise getting in contact with building control now for a site a visit and explain the situation to them, that way the solution will be to their satisfaction. P.s As above definitely sack the builder. this has only come to light because you noticed it, otherwise it would not of been mentioned, obviously the guy is not very honest.
Answered3 May 2018

Like

7

Anonymous user

I would be persuing the builder legally , as the job is not fit for purpose ! with the DPC above the floor level , wet weather will almost guarantee the blockwork below DPC will be damp , and by the sound of it , directly behind the skirting ! The job needs doing properly , there is no easy fix . Not too long ago I did remedial work to an extension with the exact same mistake . The job is time consuming , but not hard ! It may be that the finished ground level around the extension may need addressing also , to maintain 150mm below the correctly installed DPC . As for the joists ? Dwarf walls , laid to a footing and honeycombed , with airbricks allowing a crossdraft . They make for a firmer floor than hangers imho. Your builder hasn't notified building control when he should have , they would have picked up on this and am fairly sure they will demand it done right when they see it , They certainly would where I live ! If as you say , he is a reputable builder , it would certainly be in his interest to wipe his mouth and put this right . I'm pretty sure the courts would see it this way too ? good luck !
Answered26 June 2019

Like

7

Anonymous user

I would be inclined to incorporate a sleeper wall set up, but you will have to survey the oversite first. If your builder has made a lash up of D.P.C installation then yes, keep the suspended floor independant from the blockwork. Thats the only way to stop and future potential rot and decay to joist ends. last thing you need is Dry-rot accuring. Sack your builder!!
Answered13 September 2011

Like

4

J M Norfolk Building and Groundwork

No reviews yet

Guildford
Quite simply get building control involved.
Answered9 May 2020

Like

3

MD BUILDERS
Rating: 5 out of 5555 reviews
Charlton, London
If i was paying a builder for something i'd want it done correct. get him back and tell him to knock it down [ at his expense ] some of us time served builders may be a bit more expensive but you get what you pay for .its one of lifes little lessons. hope this helps
Answered29 December 2020

Like

1

C&C Construction
C&C Construction
Rating: 4.9 out of 54.9530 reviews
St Albans
Well dpc not 150mm above external ground level I’ve not heard of that even by the worst so called Builders so that needs a dpc correctly installed higher up lapping into existing House dpc so continuation of dpc the joist if you’re talking suspended timber floor should be a min distance from bottom to floor beneath and wall timber they are hung from will need dpc behind that is attached to floor dpc I suspect building control will ask for this or advise what should be done before proceeding
Answered30 June 2018

Like

0

Carlton

No reviews yet

Truro
Exposed Timber should never be touching any bricks below DPC this will result in damp rotting timber and fungal growth.
Answered15 August 2023

Like

0

Anonymous user

Hiya, sorry but start again, talk to building control at local authority they will give you better advice as to what they and you can do, good luck 🤞
Answered20 August 2023

Like

0

Anonymous user

Hi everyone
Answered6 December 2023

Like

0

Anonymous user

If this is a cavity wall damp height should be at w levels bottom of joist and 10mm below floor height joists would of been better treated or wrapped in dpm built into brickwork /blockwork , surely architect plans would of shown floor detail
Answered26 January 2024

Like

0