taking down wall need RSJ opening is 3m600 wide holding up red brick wall above which is 1 storey high, what depth and width of RSJ is required

Anonymous user 03/03/2024 - 2.47 PM

Are you a tradesperson and able to answer this question?

3 Answers

Roc builders

Rating: 5 out of 5
Harlow
Structural engineer for this one.Anything else and you will not get it signed off by building control.
Answered22 January 2012
5

Anonymous user

GET A STRUCTURAL ENGINEER TO DO CALCS FOR YOU
Answered22 January 2012
4

Paul Callaghan Builder

Rating: 5 out of 5
Romsey
Hi, Building control must be involved in the job, ask when they make there d.p.c site vist, they should tell you there preference, although either would actually do the job. Regards Paul
Answered2 March 2012